Hot-Dip Galvanized PV Racking: Field Coating Repair Checks
A damaged coating area on a delivered steel member needs a recorded decision before it disappears inside an assembled rack. For EPCs and installers, a clear repair package connects the observed damage, approved method and inspection evidence.
Confirm the coating system first
Check the purchase documents and supplier records to identify whether the member is hot-dip galvanized after fabrication. Record any additional paint system. For sheet-coated products such as zinc-aluminum-magnesium steel, obtain the product-specific treatment instructions from the supplier. Keep each product designation attached to its inspection record.
Map the damage before work starts
Photograph the affected area with a scale and identify the part number, member location and delivery batch. Record approximate dimensions and whether the surface is accessible after assembly. Ask the supplier and responsible project reviewer to determine the disposition under the applicable coating specification.
Include nearby distortion or weld damage in the report so the reviewer can assess the member as well as its coating. Hold the affected item until the accepted disposition is available.
Specify the approved repair procedure
The American Galvanizers Association explains that ASTM A780 addresses three repair approaches for hot-dip galvanized coatings, using zinc-rich paint, zinc-based solder or zinc metallizing. Method selection should consider the intended use and performance requirements. [1]
Request the named repair product, preparation procedure, application conditions, required thickness, curing requirements and inspection method. AGA guidance for zinc-rich paint emphasizes surface preparation and a clean, dry substrate. [2] Use the project’s applicable standard edition and the accepted product instructions to set the actual requirements.
Inspect before the area becomes concealed
- Record preparation and application against the approved procedure.
- Retain the repair product identification and application date.
- Document the specified thickness checks and any other required inspection results.
- Photograph the finished area and obtain acceptance before covering the detail.
If the approved preparation or inspection cannot be achieved at the assembled location, refer the access problem for a revised disposition before proceeding. Avoid extending an accepted repair detail to other coating systems without supplier review.
Close the record with the delivered member
Attach the accepted repair record to the batch or member identifier in the handover file. This gives later inspections a location, procedure and baseline to compare. Clear documentation also lets procurement distinguish an unresolved delivery defect from a completed and accepted repair.