A box marked “spare clamps” gives a maintenance team little help when the installed array contains several clamp versions. EPCs and distributors can make future replacement work easier by handing over a register that connects each spare to the approved installation detail.

Start from the installed configuration

Use the accepted bill of materials and as-built drawings to identify the mounting components actually installed. Record complete supplier part numbers, descriptions, finishes and relevant drawing references. Include approved substitutions so the register reflects the completed array.

DOE guidance for PV operations and maintenance calls for as-built documentation, equipment manuals and an inventory of accessible spare parts. It also recommends a process for deciding when to order additional spares based on component failure history. [1]

Give each stock item an unambiguous identity

As a suggested register format, include the following fields.

  • Supplier name, complete part number and product revision where applicable.
  • Accepted assembly or drawing reference and the locations where the item is used.
  • Quantity held, storage location and purchase date.
  • Supporting manual or supplier confirmation and the person responsible for replenishment.

The NREL O&M best-practices report specifically recommends tracking spare-part names and numbers, stock counts, locations and purchase dates. [2] A dated photograph of the label can supplement the register when packaging identifiers are difficult to read.

Keep substitutions in the review process

When an original component is unavailable, send the proposed replacement and installed assembly details to the responsible reviewer. Request written acceptance before releasing the replacement for use. Keep the decision with the stock record and revise the drawing reference where required.

For example, a clamp with a similar appearance may arrive under a different part number. Flag the difference at receiving and resolve its intended application before mixing it with existing stock.

Record each issue from stores

Log the quantity issued, work-order number, array location and remaining balance. Ask the maintenance team to record the installed replacement and any associated inspection required by the accepted procedure. Link returned or damaged items to that work order so they can receive a disposition.

Hand over a register someone can maintain

Assign an owner and agree how stock counts and supplier availability will be reviewed. Deliver the register with its supporting documents in the project file. Consistent identifiers let the next team connect a storage-bin label to an accepted mounting detail and a completed maintenance record.

Sources

  1. U.S. DOE FEMP — Optimizing Solar Photovoltaic Performance for Longevity
  2. NREL — Best Practices for Operation and Maintenance of Photovoltaic and Energy Storage Systems, Third Edition